Work Order Package
Contractor logo
(applies to all pages)
Work Order Request
Repair & Troubleshooting – Fiber Infrastructure
Customer logo
Project:S. Matlock Rd – South of Green Oaks Blvd
Date:July 6, 2026
Location:Matlock Rd corridor south of Green Oaks Blvd (see attached map)
Requested By:Precision Networks
Customer:City of Arlington – Public Works & Information Technology Departments
Scope of Work – Repair & Troubleshooting
1. Site investigation and troubleshooting of fiber infrastructure along S. Matlock Rd south of Green Oaks Blvd. 2. Locate and expose damaged or compromised conduit sections as identified on attached map. 3. Perform necessary repairs to restore continuous fiber pathway (conduit repair, splicing, or re-routing as required). 4. Test and verify fiber continuity and signal integrity after repairs are completed. 5. Document all findings, repairs performed, and provide as-built updates. 6. Coordinate with City of Arlington representatives for inspection and approval of completed work.
Notes & Assumptions
• Work to be performed during normal business hours unless otherwise requested by the City. • Traffic control and permitting (if required) to be coordinated with City of Arlington. • Any additional damage or scope discovered during investigation will be documented and quoted separately. • All work will be performed in accordance with City of Arlington specifications and industry standards.
Authorization
Requested By (Precision Networks):Date:
Approved By (City of Arlington):Date:
WORK ORDER REQUEST | S. Matlock Rd – South of Green Oaks Blvd | Precision Networks for City of Arlington
CONFIDENTIAL – For Official Use Only | Page 1
Contractor logo
OTDR Test Results – Evidence of Physical Fiber Damage
Bidirectional Testing – Fiber #7 & #8 | Matlock Rd South of Green Oaks Blvd
Customer logo
Fiber #7 & #8 – South Direction (FDC: MTLK-GOB)
+ Upload OTDR trace
(Fiber #7 South)
Fiber #7 South — major event at ~1,682 ft
+ Upload OTDR trace
(Fiber #8 South)
Fiber #8 South — 0.772 dB loss at 1,643 ft + high attenuation
Key Findings from South Direction Traces:
• Clear physical damage confirmed on both Fiber #7 and #8 at approximately 1,643 ft from the test location. • Fiber #8 shows 0.772 dB loss event + high attenuation section (0.700 dB/km) 38 ft past the enclosure. • Damage location matches reported third-party impact (AT&T contractor bored through conduit). • Fiber 7 was broken inside splice enclosure in order to isolate damage and confirm damage location.
MATLOCK FIBER REPAIR PACKAGE | OTDR EVIDENCE | Page 2
Contractor logo
OTDR Test Results – Bidirectional Confirmation (North Direction)
Fiber #7 & #8 – North Direction (TSC: MTLK-NLOWE)
Customer logo
+ Upload OTDR trace
(Fiber #7 North)
Fiber #7 North
+ Upload OTDR trace
(Fiber #8 North)
Fiber #8 North — high loss 1.475 dB event confirmed
Bidirectional Confirmation – Physical Damage Verified
• Testing from both directions confirms the same physical damage location on the Matlock corridor. • Fiber #8 North shows 1.475 dB loss event, consistent with a significant physical break or crush in the fiber. • OTDR traces were taken from Traffic Signal Cabinets North and South of the Fiber Damage. • This is third-party damage (AT&T contractor) and is not related to Precision Networks installation activities.
MATLOCK FIBER REPAIR PACKAGE | OTDR EVIDENCE | Page 3
Contractor logo
Field Photo Log – Damage Documentation
Matlock Rd South of Green Oaks Blvd | Third-Party Damage by AT&T Contractor
Customer logo
Documented Damage
+ Add field photo(s)
Notes for Photo Log:
• Recommended photos: Excavation showing damaged conduit, concrete pier over conduit, red markings, exposed fiber, splice location, and overall site conditions. • All photos should include date, location reference, and description. Add as many additional pages as needed for field documentation.
MATLOCK FIBER REPAIR PACKAGE | PHOTO LOG | Page 4
+ Upload map image
(GIS export, marked-up aerial, route drawing — full page)
Drawn By
John Carlson
Location
S. Matlock South of Green Oaks
System ID
Primary Segment
Build
Secondary Segment
SMF
Customer
City of Arlington
Project
NPD-FIBER
Date
7/6/2026
Doc File
NPD-FIBER-PRINT
Pages
1 OF 1
Contractor logo
Repair & Troubleshooting Price Quote
S. Matlock Rd – South of Green Oaks Blvd | July 6, 2026
Customer logo
Labor
Description Qty Unit Price Amount
Labor Subtotal:$0.00
Materials
Description Qty Unit Price Amount
Materials Subtotal:$0.00
Total Work Order Amount$0.00
Price Quote Notes:
• This quote is valid for 30 days from the date above. • Work will be billed on a time & materials basis. Actual quantities may vary based on field conditions. • Any additional repairs or scope beyond this estimate will be quoted separately and require City approval. • Mobilization and traffic control (if required) are included in the labor rates above. • All work performed in accordance with City of Arlington standards and applicable codes.
REPAIR & TROUBLESHOOTING PRICE QUOTE | S. Matlock Rd – South of Green Oaks Blvd | Precision Networks
CONFIDENTIAL – For Official Use Only